The council has been monitoring noise levels at the Fullabrook windfarm to ensure the development meets its planning conditions not to exceed certain levels.
On this page you will find all the relevant documents relating to the noise monitoring at Fullabrook in chronological order.
Historical documents:
- October 2007 - Planning Conditions
- September 2012 - Hayes McKenzie noise monitoring report 2467/R2 - submitted by ESBI
- October 2012 - Review of report 2467/R2 - undertaken by Bob Davies for NDC
- August 2014 - Noise monitoring report 2761/R1 - submitted by ESBI
- September 2014 - Review of report 2761/R1 - undertaken by Bob Davies for NDC
- November 2014 - Letter from NDC Chief Executive to ESBI
- December 2014 - ESBI's response to letter from NDC Chief Executive
- February 2015 - Public Meeting Minutes
- June 2015 - Letter from Bob Davies to NDC re monitoring positions being representative of site as a whole
- June 2015 - Covering letter re submission of Noise Mitigation documents - sent from ESBI to NDC
- June 2015 - Explanation of Noise Mitigation documents - sent from ESBI to NDC
- June 2015 - Vestas Implementation Report - sent from ESBI to NDC
- June 2015 - WTG Shutdown Events - sent from ESBI to NDC
- August 2015 - Check Noise Monitoring Report - undertaken by Bob Davies on behalf of NDC
- September 2015 - Letter from Bob Davies to NDC re ESBI's implementation of previously agreed noise mitigation strategy
- September 2015 - public meeting minutes
- September 2015 - Timeline
- Update of UK Shadow Flicker Evidence Base
- October 2015 - Hayes McKenzie noise monitoring report submitted by ESBI
- November 2015 - response from Bob Davies re. suitability of check monitoring exercise
- December 2015 - Review of Oct 2015 Hayes Mackenzie report by Bob Davies for NDC
- February 2016 - Timeline
- February 2016 - Minutes of the public meeting
- March 2016 - extract from last year's maintenance schedule